1. Pre-prepared:
a)Clean up debris around the mill impeding the operation, checking safety facilities are completed properly.
b)Check whether there has been a dangerous location in the machine!
c)Check the ground surface to the grate plate center distance (that checks fill rate) whether it is in line with requirements;
d)Check anchor bolts, liner bolts, cylinder bolts connected with the hollow shaft, large gear connected whether there is loosening bolts, if loose should be tightened;
e)Solid manhole cover will be secured tightly.
f)The lubricants must be filled .
2. Boot sequence:
a)Starting out conveying equipment;
b)Activate the mill. (If no prior material exists within the mill, then starting the same time as starting feed mill equipment)
3 Parking order
a)To stop the feed mill equipment;
b)Stop grinding;
c)Stop discharging conveying equipment.
4. Handling Precautions
a)After the mill stops, turn the mill semi-circle every 5-10 minutes, until the mill is cool, in order to prevent generating too high a temperature stress on shaft of endcovers.
b)Always check the adequacy of the bearing lubricant;
c)If there is a long time of stop, balls should be poured out to prevent the deforming of the cylinder.